Updates for the Drawing, Painting and Photography (DPP) building and Thesis Studio building
1. Most plywood backing is on the walls of both buildings
2. Drywall work has progressed in the Thesis Building and is soon to start in the DPP Bldg.
3. Elevator installation continues in DPP
4. HVAC system are 100% roughed in.
5. Most light fixtures are now roughed in
6. Final work at the main entry is soon to be completed with only one lane to be open while the final paving starts
7. Paving of the finish lift of asphalt on the lower parking lot is scheduled in May.
8. Sidewalks and seating are now 95% complete
9. Aluminum storefront system and doors are now installed.
10. Cellulose insulation is installed waiting for the moisture content to drop to design thresholds.
11. Both buildings are being dried out with temporary heat systems

| February 2012 | ||||||
|---|---|---|---|---|---|---|
| S | M | T | W | T | F | S |
| 1 | 2 | 3 | 4 | |||
| 5 | 6 | 7 | 8 | 9 | 10 | 11 |
| 12 | 13 | 14 | 15 | 16 | 17 | 18 |
| 19 | 20 | 21 | 22 | 23 | 24 | 25 |
| 26 | 27 | 28 | 29 | |||