OCAC BLOG
Tuesday, June 29, 2010

OCAC Construction Update :: July 2010

Construction on the new Drawing, Painting and Photography Building and adjacent Thesis Studio Building is rolling along. The finish work is in full swing to meet the August 2010 completion date.

1.  The 2nd lift of paving was installed at the lower parking lot & entry

image
2.  Tile work is done in the DPP toilet rooms and in progress at the Thesis Bldg.

image
3.  Tack boards are being installed at DPP on both levels

4.  Cabinet installation is beginning

image
5.  Plaster work in the Gallery area of DPP is being installed

image
6.  Drywall work is nearing completions

7.  Painting is happenning at DPP and Thesis

image
8.  Light fixtures ready to be installed

9.  Orchard pump is in place ready for grading work