OCAC Construction Update :: June 2010

image

1.  Drywall at Drawing, Painting, Photography & Thesis Building is 90% complete.


image

2.  Metal art railings designed by artist Linda Hutchins are being installed.


image

3.  All mechanical and electrical rough-ins are complete and finishes will start as soon as painting is completed.


image

4.  The final layer of asphalt for the parking lots has been scheduled for the next two days of good weather.

5.  Tack boards are being installed at DPP and Thesis buildings.