Electrical Light Poles in the parking lot are now installed and electrical switch gear is being install to prepare for PGE connection.
Excavation for sidewalks around the perimeter of campus is underway.
Cedar siding continues to be installed at Thesis Building and soffit of covered walkways.
Backfill is being installed and concrete is being poured for upper courtyard/plaza.
Storefront windows continue to be installed on both the Thesis and Drawing, Painting and Photography (DPP) buildings.
Next entry: Student News :: January 2010
Previous entry: Faculty News :: January 2010

| May 2012 | ||||||
|---|---|---|---|---|---|---|
| S | M | T | W | T | F | S |
| 1 | 2 | 3 | 4 | 5 | ||
| 6 | 7 | 8 | 9 | 10 | 11 | 12 |
| 13 | 14 | 15 | 16 | 17 | 18 | 19 |
| 20 | 21 | 22 | 23 | 24 | 25 | 26 |
| 27 | 28 | 29 | 30 | 31 | ||



