Offsite Inprovments have started on:
• SW Barnes Road where new sidewalks, lighting, and a divided entry will be installed at OCAC’s main entry.
• SW Leahy Road where new sidewalks will be installed along the perimeter of the OCAC property.
• SW 84th where new culverts and improvments to the storm water ditches has already been completed.
Thesis Building:
• Wood siding is in progress on the Thesis building over an Air-barrier.
• Glass is being installed at the Thesis window wall systems.
• Interiors of the Thesis space is framed and ready for electrical work to start.
• Stairs to the roof deck of the Thesis space are now ready for the precast concrete steps to be installed.
Drawing, Painting and Photography (DPP) Building:
• The concrete stairs connecting to the upper courtyard have been poured.
• Concrete retaining walls for the new ramp/sidewalk along the uper side of the DPP Bldg. have been poured.
• Landscaping at the lower level parking lot is ready for plantings.
• The glass monitors in the DPP Bldg. are 90% installed.
• The custom darkroom sinks for the Photograpy Dept. have been set into each room.
• Installation of the air Barrier is ready to start on the DPP Bldg.
• Washington County has approved final structural design revision to the DPP building storefront glazing system.
• Artist’s commissions for elevator lobby, lower level conference room and railings are in progess.
Next entry: OCAC Ceramics Guild Holiday Sale
Previous entry: Free display space in Portland

| July 2010 | ||||||
|---|---|---|---|---|---|---|
| S | M | T | W | T | F | S |
| 1 | 2 | 3 | ||||
| 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| 11 | 12 | 13 | 14 | 15 | 16 | 17 |
| 18 | 19 | 20 | 21 | 22 | 23 | 24 |
| 25 | 26 | 27 | 28 | 29 | 30 | 31 |